Metro will close the entire D (Purple) Line subway for 70 days beginning Saturday so crews can connect the existing line to its planned extension to West Los Angeles. The closure, which will begin at ...
The entire D (Purple) Line subway was closed Saturday and will remain out of service for 70 days so crews can connect the existing line to its planned extension to West Los Angeles. The closure, which ...
Los Angeles Metro’s D Line (the purple one) will be closed from May 17 to July 25 to complete the first leg of the extension. Three new D Line stops should be ready for riders later this year. Why: ...
Metro will close the entire D (Purple) Line subway for 70 days beginning at 9 p.m. May 17 so crews can connect the existing line to its planned extension to West Los Angeles. The closure, which will ...